Illustration 11.

मैसर्स ए० के० गर्ग एण्ड सन्स, बुलन्दशहर एक भवन ठेकेदारों की फर्म ने । अप्रैल, 2018 से अपना व्यापार शुरू किया 6,00,000 के एक ठेके निम्नलिखित व्यय थे

M/s. A.K. Garg & Sons, Bulandshahr a firm of building contractors, began to trade on 1st April, 2018. The following was the expenditure on a contract for 6,00,000 : Materials issued to contract for 6,00,000

Materials issued to contract                                    1,00,000

Plant used for contract                                               30,000

Wages paid                                                                      1,60,000

Other Office expenses paid                                          10,000

31 मार्च, 2019 तक इस खाते पर 2,56,000 प्राप्त हुये जो कि प्रमाणित कार्य का 80 %  था । ठेके पर लगाये गये संयन्त्र और सामग्री में से 6,000  की लागत का संयन्त्र और 1,000 की लाग का सामग्री नष्ट हो गयी । 31 मार्च 2019 को 4,000 की लागत का संयन्त्र स्टोर्स को वापस किया गया । अप्रमाणित कार्य की लागत 2,000 तथा ठेके पर बची सामग्री की लागत 4,600 थी ।

संयन्त्र पर 15% ह्रास लगाइये तथा उक्त विवरण से एक ठेका खाता बनाइये।

Cash received on account to 31st March, 2019 amounted to 2,56,000 being 80% of the work certified. Of the plant and materials charged to the contract, plant which cost 6,000 and materials which cost 1,000 were lost. On 31st March, 2019. plant which cost 4,000 was returned to store. The cost of work done but uncertified was 2,000 and materials costing 4,600 were in hand on site.

Charge 15% depreciation on plant and prepare a Contract Account from the above particulars.

BCom 2nd Year Cost Accounting Books of Contractor Study Material Notes in Hindi (Part 2)
BCom 2nd Year Cost Accounting Books of Contractor Study Material Notes in Hindi (Part 2)

आकस्मिकताओं या सम्भाव्यताओं के लिये संचय (Reserve for Contingencies)-कभी-कभी टेके पर अति कुल लाभ में से कुछ रकम आकस्मिकताओं के लिये संचय में हस्तान्तरित करने का स्पष्ट निर्देश दिया हुआ होता है। ऐसी दशा में लाभ-हानि खाते में क्रेडिट को जाने वाली रकम की गणना तो पहले की तरह ही करते है। केवल संचय के रूप में रखे गये लाभ के दो भाग कर देते है-एक आकस्मिकताओं हेतु संचय, दूसरा सामान्य संचय। आकस्मिकताओं हेतु संचय को। गणना हेतु प्रश्न में दिये हुये निर्देश का पालन किया जाता है।

Bcom 2nd Year Cost Accounting Books of Contractor Study Material Notes in Hindi

Illustration12.

भवन ठेकेदारों की एक फर्म ने 1 अप्रैल, 2018 को व्यापार आरम्भ किया। 4,50,000 ₹ के ठेके पर निम्नलिखित व्यय हुआ ।

A firm of building contractors began to trade on 1st April, 2018. The following was the expenditure on the contract for:

सामग्री ठेके को निर्गमित (Materials issued to contract)                        76,500

ठेके हेतु प्रयुक्त प्लाण्ट (Plant used for contract)                                        22,500

पारिश्रमिक दिया गया (Wages incurred)                                                      1,21,500

अन्य व्यय हुये (Other expenses incurred).                                                  7,500

31 मार्च, 2019 तक प्रमाणित कार्य के 80% के हिसाब से 1.92.000१ नकद इस खाते पर प्राप्त हुआ। ठेके को चार्ज किये प्लाण्ट व सामग्री में से 4,500 ₹ की लागत का प्लाण्ट व 3,750₹ की लागत की सामग्री खो गयी। 31 मार्च, 2019 को 3,000 ₹ की लागत का प्लाण्ट स्टोर्स को लौटा दिया, किये गये परन्तु अप्रमाणित कार्य की लागत 1,500₹ थी और 3,450₹ की लागत की सामग्री स्थल पर हाथ में थी। प्लाण्ट पर 15% हास लगाना है। अर्जित लाभों का 10 संचित कीजिए और उपर्युक्त विवरण से ठेका खाता तैयार

करो।

Cash received on account to 31st March, 2019 amounted to ? 1.92,000 being 80% of the work certified, or the plant and materials charged to the contract, plant which cost 4,500 and materials which cost <3,750 were lost. On 31st March, 2019 plant which cost 3,000 was returned to stores. the cost of work done but uncertified was? 1,500 and materials costing?3,450 were in hand on site.

Charge 15% depreciation on plant. Reserve 1/3 of profit earned and prepare a Contract Account from the above particulars.

BCom 2nd Year Cost Accounting Books of Contractor Study Material Notes in Hindi (Part 2)
BCom 2nd Year Cost Accounting Books of Contractor Study Material Notes in Hindi (Part 2)

प्रदत्त तलपट से ठेका खाता एवं चिट्ठा बनाना-कभी-कभी ठेकेदार की लेखा पुस्तकों के आधार पर तैयार किया हुआ तलपट एवं ठेके से सम्बन्धित सूचनायें दी हुई होती हैं। ऐसी दशा में ठेके खाते में केवल ठेके से सम्बन्धित सूचनाओं का ही प्रयोग किया जाता है, अन्य मदों को यथास्थान चिठे में लिखा जाता है। निम्नलिखित उदाहरण द्वारा इसे भली प्रकार समझा जा सकता है

Illustration 13.

31 मार्च, 2019 को समाप्त होने वाले वर्ष के लिए शरद कम्पनी लिमिटेड की पुस्तकें निम्नलिखित सूचनाएं प्रदर्शित करती है

ठेके से चार्ज किये गये प्लाण्ट व सामग्री से, प्लाण्ट जिसकी लागत 3,000 ₹ थी तथा सामग्री जिसकी लागत 2,400₹ थी, खो गई। 31 मार्च, 2019 को 3,000 ₹ का प्लाण्ट स्टोर्स को वापस कर दिया गया। कार्यस्थल पर सामग्री का मूल्य 2,400₹ था। अप्रमाणित कार्य की लागत 1,200 ₹ थी। ठेका मूल्य 3,00,000 १ का था। प्लाण्ट पर 10% हास लगाइये तथा निम्न तलपट से ठेका खाता, चालू कार्य खाता एवं चिट्ठा 31 मार्च, 2019 को बनाइए।

The following figures are extracted from the books of Sharad Company Ltd. for the year ending 31st March 2019:

Of the plant and materials charged to the contract the plant whose cost was 3,000 and materials costing 2,400 were lost. On 31st March, 2019, the plant of the cost of 3,000 was returned to the stores. Materials costing ₹2,400 were in site. The cost of work uncertified was. 1,200. The contract price was 3,00,000. Charge 10% depreciation on plant and prepare Contract Account, Work-inProgress Account and Balance Sheet on 31st March, 2019 from the following trial balance :

BCom 2nd Year Cost Accounting Books of Contractor Study Material Notes in Hindi (Part 2)
BCom 2nd Year Cost Accounting Books of Contractor Study Material Notes in Hindi (Part 2)

 

दो या अधिक ठेके (Two or More Contracts)-यदि कोई ठेकेदार एक ही वित्तीय वर्ष में अनेक ठेके लेता है तो परेक ठेके के लिये अलग-अलग ठेका खाता बनाया जा सकता है और यदि ठेकों की संख्या अधिक नहीं है तो सभी ठेको लिये स्तम्भाकार रूप में भी ठेका खाता बनाया जा सकता है। विभिन्न ठेकों के लिये अलग-अलग ठेका खाता बनाया जाये अथवा स्तम्भाकार रूप में ठेका खाता बनाया जाये, चिट्ठे में सभी ठेकों की मदें एक ही स्थान पर दर्शायी जाती है। ठेके खाते तैयार करने के लिये पूर्व वर्णित सामान्य नियमों का ही अनुसरण किया जाता है।

Bcom 2nd Year Cost Accounting Books of Contractor Study Material Notes in Hindi

chetansati

Admin

https://gurujionlinestudy.com

Leave a Reply

Your email address will not be published.

Previous Story

Bcom 2nd Year Cost Accounting Contract Cost Study Material Notes In Hindi( Part 1)

Next Story

Bcom 2nd Year Cost Accounting Contract Account Study Material Notes In Hindi ( Part 3)

Latest from B.Com